Kochi Maradu case: SC directs demolition to be completed in 138 days

Date:

The Supreme Court said that demolition of flats built on the coastal zone of Kochi’s Maradu to be completed in 138 days, in accordance with the Kerala government schedule.

The top court added that directed payment of Rs 25 lakh as interim compensation to each flat owner within four weeks duration.

ALSO READ: Jailed for 63 child deaths in 2017 Gorakhpur hospital tragedy, Dr Kafeel Khan gets clean chit

The apex court ordered setting up of a one-member committee of retired high court judge to look after the demolition and assess compensation.

A bench comprising justices Arun Mishra and S Ravindra Bhat directed freezing of assets of builders who were involved in the construction of illegal buildings in the coastal zones of Kochi.

The bench further said the government may consider recovering the interim compensation amount from builders and promoters.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

Popular

More like this
Related

News Mobile Morning Brief

Lok Sabha Phase 4 Records 63.04% Voter Turnout New Delhi:...

IPL 2024: GT Eliminated From Playoff Race As Match Against KKR Abandoned Due To Rain

Ahmedabad: Shubman Gill's Gujarat Titans faced a disappointing blow...

Ex-Bihar Deputy CM Sushil Kumar Modi Passes Away

New Delhi: Former Bihar Deputy Chief Minister and Senior...